Boduthakurufaanu Magu project enters final stages of phase one works

18 Jul 2026

|

Aishath Shaaleen

Boduthakurufaanu Magu -- Photo: MTCC

Cable trench installation has been completed under the Phase One redevelopment of Boduthakurufaanu Magu. Maldives Transport and Contracting Company (MTCC) said construction of the parking zone and sidewalk paving on Segments 2 and 3 is progressing rapidly. The company added that road marking works and the raising of junction utilities on Segments 2 and 3 are currently underway and are expected to be completed within the week. MTCC said work is continuing as scheduled to complete the remaining components of the first phase of the project.